AI Data Centers Compete for Power, Stalling U.S. Aluminum Revival
nashnova research
A shuttered New York smelter is being converted into a 635 MW data center, spotlighting a widening power struggle between AI infrastructure and U.S. manufacturing — data centers can pay nearly three times the electricity price aluminum plants need, leaving domestic smelting with almost no path to compete.
Why is a dead aluminum plant becoming a data center?
Alcoa shut its Massena East smelter in 2014, cutting 84,000 tonnes of annual capacity — one of the largest closures in U.S. aluminum history.
New York Digital Investment Group (NYDIG) now plans to convert the site into a data center drawing 635 MW — enough to power more than 500,000 American homes.
This means → old smelters sit on ready-made, high-capacity grid connections, giving data-center developers a plug-and-play site far cheaper than building from scratch.
How big is the data-center building boom?
Columbia Business School economist Stijn Van Nieuwerburgh estimates the total cost of building data centers, power sources, and compute hardware will approach $9 trillion by 2032.
In plain terms = measured as a share of GDP, this wave of spending would surpass the 19th-century railroad boom.
This reflects a shift: AI infrastructure is no longer one industry's capex — it is a systemic expansion reshaping the U.S. energy landscape.
Why can't aluminum plants outbid data centers?
According to SAFE's Industrial Materials Center, a new U.S. smelter needs long-term power at roughly $40 per MWh to be globally competitive.
Data centers can pay up to about $115 per MWh — nearly three times the aluminum threshold.
This means → on the same grid, aluminum cannot win the bidding war. In plain terms = data centers can afford electricity bills that smelters simply cannot match.
Can tariffs and subsidies rescue U.S. aluminum?
The Trump administration imposed tariffs on imported aluminum and backed a $4 billion smelter in Oklahoma — the first new U.S. smelter since 1980.
Yet Alcoa's actual move this year was to spend $5.6 billion acquiring South32's aluminum and alumina assets in Australia, Brazil, and South Africa — not to expand at home.
This reflects the industry's pessimism about domestic economics: tariffs can block imports, but they cannot close the electricity-cost gap.
Where does this power struggle go from here?
Retired smelters, with their built-in high-capacity grid access, are becoming priority acquisition targets for data-center developers — further squeezing the cheap power aluminum would need to restart.
Joe Quinn, head of SAFE's Industrial Materials Center, put it plainly: "Data centers have an extremely high appetite for power, and aluminum producers no longer have the same incentive to build in the U.S."
This means → the power contest between aluminum and AI infrastructure is shaping up as a critical test of whether Trump's manufacturing-reshoring strategy can actually work.