Brookfield Plans $27 Billion Investment to Build AI Data Centers in England
nashnova research
Brookfield is partnering with energy firm Drax to build an AI data center at Drax's North Yorkshire power station, with total investment potentially exceeding £20 billion (~$26.8 billion) — Drax shares jumped 8.2% on the news as Europe's AI infrastructure race enters its 'power plant to data center' phase.
What is this deal?
Energy company Drax Group signed an agreement with Brookfield Asset Management and its cloud platform Radiant to jointly develop an AI data center inside the Drax power station campus.
Total investment — including semiconductors — could exceed £20 billion (~$26.8 billion). The first phase alone is about £2.5 billion.
This means → a single project approaching the largest AI infrastructure investments in Europe. Brookfield is channeling asset-management scale directly into compute.
Why build inside a power station?
The Drax campus has ready-made power supply infrastructure — the scarcest resource for large-scale data center siting.
Europe faces high energy costs and high land costs; old power station campuses with direct grid access are becoming premium assets.
In plain terms = the biggest bottleneck for data centers is not servers — it is electricity. Building next to a power station is like putting the tap right at the water source, cutting out the most expensive middle step.
What is the build timeline?
Phase one target: up to 100 MW of operating capacity by Q1 2028.
Phase two: an additional 500 MW between 2028 and 2031.
Long-term plan: total site capacity above 1 GW, with no specific date set.
This means → the first-phase delivery is the signal light for the entire plan. Whether it lands on schedule in 2028 determines whether the remaining tens of billions keep flowing.
How did the market react?
After the announcement, Drax's London-listed shares rose as much as 8.2% in early trading.
This reflects a market repricing of the "legacy energy asset + AI demand" combination — traditional energy companies with grid access are being treated as gateways to AI infrastructure.
Put simply = Drax used to sell electricity. Now it sells "electricity for compute," and the valuation logic has shifted from energy stock to AI infrastructure stock.
市场有风险,内容仅供研究参考,不构成投资建议。