Core Scientific Registers $1.3B AMD Data Center, Races to Break Ground Before New Texas Regulations
nashnova research
Core Scientific's subsidiary filed a $1.3 billion data center in Hunt County, Texas, with a November 24 construction start — exactly eight weeks before the incoming governor's promised permit freeze takes effect, making it the first real-world test of Wall Street's assumption that projects already under way will be exempt.
What is being built, and how much does it cost?
Telios Quinlan One, a Core Scientific subsidiary, registered a new data center in Quinlan, Hunt County — about 85 km northeast of Dallas. Floor area: roughly 341,000 sq ft. Estimated cost: $1.3 billion.
This means → at management's disclosed build cost of $11–12 million per MW, $1.3 billion maps to roughly 108–118 MW — closely matching AMD's ~110 MW lease in Hunt County.
In plain terms = this facility is essentially purpose-built for AMD; the dollars and the power capacity line up almost exactly.
Why start construction on November 24 specifically?
The planned start date of November 24, 2026 falls exactly eight weeks before governor-elect Gina Hinojosa's January 19, 2027 inauguration.
Hinojosa campaigned on freezing data center approvals until the legislature writes new rules. Post-election, she went further: the freeze covers "all permits," not just new applications.
This means → once the new governor takes office, even filed-but-unstarted projects could be frozen. Breaking ground before inauguration is a bet that "already under construction" equals "exempt."
How are Core Scientific and AMD connected?
In May, Core Scientific paid $232.5 million to acquire Telios Quinlan One, funded by selling 2,385 bitcoin. The entity holds roughly 265 acres of land and a ~430 MW power-service agreement with a local electric cooperative.
In July, AMD signed a 15-year lease with Core Scientific covering ~530 MW across five campuses. Base contract revenue: over $14 billion.
In plain terms = Core Scientific used bitcoin proceeds to buy land and power, then locked AMD into a long-term lease on that power — a "bitcoin-to-data-center" asset conversion.
How tangled is the Texas regulatory picture?
In August, then-Governor Greg Abbott cited a 474 GW backlog in ERCOT's large-load interconnection queue and halted grid approvals, launching an audit.
In September, he ordered the state environmental quality commission to stop issuing data center permits; the agency shut down its online filing system.
This reflects a grid that has already hit its absorption limit — the outgoing governor was tightening the screws before the incoming one even arrived.
What does Wall Street make of all this?
Goldman Sachs chief economist Jan Hatzius estimated that Democratic wins at state level could subject roughly 45% of U.S. data center capacity under construction to a short-term pause; Texas accounts for about one-quarter of that.
The prevailing consensus is that projects already under way will be shielded from new policy. The Hunt County project is the first concrete test of that assumption.
Core Scientific shares fell roughly 7% Monday to around $13.50, down more than half from the 52-week high of $30.46. This means → the market is not giving the "race-to-start" strategy full credit; the stock is pricing in regulatory uncertainty, not a problem with the project itself.