Google's $15 Billion India AI Data Center Hit by Environmental Lawsuit
Miles Bennett
Google's $15 billion AI data center project in India, a joint effort with the Adani Group, faces multiple court challenges over water scarcity and wildlife risks — putting its 2028 first-phase launch timeline in doubt.
How big is this project?
The site is in Visakhapatnam, Andhra Pradesh, with a planned total capacity of 2.5 GW spread across three campuses.
Google is partnering with the Gautam Adani Group; Bharti Airtel provides connectivity. The rollout runs in phases from 2026 to 2030.
The first phase — a 1 GW compute data center — is slated to go live in September 2028. This means → any court-ordered delay cascades through the entire phased timeline.
What is happening in the courts?
The Andhra Pradesh High Court has admitted at least one public-interest litigation (PIL) case. The National Green Tribunal (NGT) has three separate cases pending.
Critics allege the project cleared approvals in nine days without adequate public hearings. Satellite imagery suggests construction began before formal environmental clearance was granted.
The High Court's next hearing is set for August 24. This means → that date is the first hard checkpoint for whether the project stays on schedule.
Why is water the flashpoint?
Visakhapatnam has roughly 2.5 million residents. Daily supply runs about 410 million liters, but actual demand hits 480 million liters — rationing is already routine. In plain terms = the city is short on water before a single data center goes online.
The advocacy group Jal Biradari filed a PIL alleging the project will strain the nearby Mudasarlova reservoir, worsening the deficit.
Green Visakha questioned the government's pledge to "guarantee" the project 20 years of water supply — a promise hard to square with existing rationing for ordinary residents.
What are the ecological concerns?
The construction site sits just 860 meters from the Kambalakonda Wildlife Sanctuary, home to leopards and pangolins.
The PIL argues that large-scale construction vibrations and noise could disturb wildlife inside the sanctuary.
The Human Rights Forum has filed three cases with the NGT demanding a construction halt. This reflects opposition broadening from environmental groups into the human-rights domain.
How have Google and the government responded?
Google says the project will comply with all applicable laws, use "advanced air-cooling technology," draw water from sources independent of the local drinking supply, and has already conducted environmental audits.
The Andhra Pradesh government denies the project was rushed, calling activists' concerns "inaccurate and misleading." It says the site-to-sanctuary distance exceeds the legal minimum.
Yet street protests have spread from professional advocacy groups to ordinary residents. Banners reading "We can't drink data" have appeared on social media. In plain terms = official reassurances have not calmed the backlash — they may be fueling it.
What precedent could this set?
The NGT's three pending cases could establish a benchmark for environmental review of future large-scale data center projects across India.
This means → the stakes go beyond one Google campus — the rulings may redefine the approval threshold for India's entire AI infrastructure buildout.
The most immediate question: whether Google's 2028 first-phase launch must be pushed back hinges on the August 24 hearing and subsequent rulings.