Morgan Stanley: 20% of U.S. Data Center Projects Pushed to 2029, 40% of Chips Face Power Connection Gap

nashnova research
2026-11-10发布阅读约 10 分钟

Morgan Stanley warns that political headwinds from U.S. midterm elections are pushing roughly 5 GW of data center projects from 2028 into 2029, leaving about 40% of deployed chips at risk of not powering on in time — rewriting AI infrastructure timelines.

01

How much got delayed, and what does that do to the pace?

About 5 GW of U.S. data center capacity shifts from 2028 to 2029 — roughly 20% of new capacity originally scheduled for 2028.
This means → U.S. data center additions fall 4% year-on-year in 2028, while the global total still grows 9%. The U.S. then rebounds 38% in 2029.
In plain terms = demand hasn't disappeared. America's own build-out stalls for a year; the rest of the world keeps going.
02

How big is the power gap?

Morgan Stanley's waterfall model puts total power demand from U.S. chip shipments during 2026–2028 at 116 GW.
Subtract 25 GW from data centers under construction and 21 GW of available grid capacity, then add 6 GW of new delay tied to election-related permitting — the gross gap reaches 76 GW.
Turbines, Bloom Energy fuel cells, and nuclear can cover 27 GW; shifting workloads to Asia trims another 5 GW. The net gap narrows to 44 GW — still roughly 40% of total demand.
03

Who actually has the power to block projects?

The report stresses that the policy tools capable of stalling projects sit mainly with state and local governments; federal politics has limited direct impact on individual builds.
Projects already under construction are unlikely to be disrupted by newly elected governors, so 2027 build expectations hold steady.
But some projects slated for 2028 in Texas and Ohio may slip as governors negotiate new approval requirements with state legislatures. This reflects a key reality: the real bottleneck is the statehouse, not the White House.
04

Where does the displaced capacity go?

Morgan Stanley estimates that by 2030, the U.S. will add roughly 103 GW, China about 55 GW, and Europe about 13 GW — America's market lead is not fundamentally altered by the election.
But the election results push developers to look overseas: Southeast Asia +6 GW, India +7 GW, Europe +12 GW, Australia 4+ GW, Japan +2 GW, South Korea +2 GW.
Construction costs are rising at over 10% per year. Build cost and power price are the two most important factors when choosing an overseas site.
05

Will the tech giants keep spending?

Morgan Stanley holds its capex forecasts for Alphabet, Amazon, Microsoft, and Meta unchanged: from roughly $481 billion in 2025 to about $1.64 trillion in 2027, rising further to approximately $1.76 trillion in 2028.
However, if the 2028 construction delay materializes, that year's capex could be revised down.
In plain terms = the giants haven't cut their budgets, but whether the money actually gets spent on time depends on whether power and permits can keep up.
06

What signal is the credit market sending?

Bond issuance by high-quality hyperscalers has picked up recently, but credit spreads have widened to their broadest level of the year.
Rate-sensitive data center construction debt has slowed notably; related bonds have underperformed their ratings-tier index since summer.
This means → the funding market is already sorting "whose AI story is credible" from "whose isn't." Whether the 2028 build pace recovers on schedule will be the key test of whether the AI capex cycle is being materially stretched.