Nomura Raises 2027 AI Server Revenue Forecast to $886.1B with 143% Growth; CoWoS Growth to Slow to 30% by 2028
nashnova research
Nomura lifted its 2027 global AI server revenue forecast 32% to $886.1 billion, implying 143% year-on-year growth — driven not by shipments but by price: HBM costs doubling and TSMC advanced-node hikes exceeding 10%, signaling the AI boom's engine is shifting from volume to pricing power.
$886 billion in AI server revenue — what's actually driving it?
2027 AI server shipments reach roughly 4.25 million units, up 54% YoY. But the average selling price jumps from about $1.32 million to roughly $2.08 million — a 58% increase per box.
This means → price and volume each contribute roughly half of the 143% revenue growth. Pricing power now matches shipment growth as a revenue driver.
2028 is even starker: shipments rise only 3% to 4.37 million units. In plain terms = by 2028, whether this market keeps expanding hinges on one question — can prices keep climbing?
The price sources are specific: Nomura expects HBM prices to double in 2027, TSMC advanced-node pricing to rise over 10%, with potential multiple hikes within the year.
Why are general-purpose servers getting cut instead?
Nomura trimmed 2026 general-purpose server (CPU-centric) shipment forecasts by 8% and 2027 by 15%, lowering annual growth from 25%–30% to 15%–20%.
The cause: simultaneous shortages in memory, CPUs, PCBs, IC substrates, power-management chips, and specialty passive components — with suppliers broadly prioritizing AI orders.
This reflects a supply-chain tilt already underway: AI servers are effectively taking parts away from general-purpose servers.
CoWoS capacity nearly doubles — so why does 2028 growth still drop?
Nomura holds its 2027 TSMC CoWoS — an advanced packaging process that bonds multiple chips onto one substrate — capacity forecast at roughly 2 million wafers, up nearly 80% YoY.
For 2028 it gives a first estimate: about 2.61 million wafers, with growth slowing to roughly 30%. Nomura builds in a ~10% output buffer, citing component shortages in 2027 and regulatory uncertainty around data-center deployment in 2028.
Nvidia's share edges down from 56%–58% in 2026 to 52%–54% in 2028, yet its absolute allocation still grows from 350K–370K wafers in 2025 to 1.22M–1.27M wafers in 2028. This means → Nvidia's slice of the pie shrinks, but the pie triples — it walks away with far more capacity than before.
Why are Google's and AMD's CoWoS shares shifting so sharply?
Google (including Broadcom and MediaTek) sees the largest share jump, from about 20% in 2026 to roughly 28% in 2027 — about 500K wafers, up over 119% YoY. The driver: Google TPU shipments rising from roughly 3.8 million units in 2026 to about 8.8 million in 2027.
But Google's share retreats to about 24% in 2028 — because TPU v9, led by MediaTek, shifts to Intel's EMIB-T packaging (Intel's own chip-stitching technology) and no longer uses TSMC CoWoS. This means → a single major client's technology-roadmap decision can visibly reshape TSMC's CoWoS customer mix.
AMD's share rises from 7%–8% in 2026 to 10%–11% in 2028, with CoWoS allocation growing from 135K wafers in 2027 to 250K wafers in 2028 — absorbing MI450 deployment plans from OpenAI and Meta (6GW each) and Anthropic (2GW).
How did SpaceX become the biggest wild card?
Nomura believes SpaceX has been Nvidia's single largest customer since H2 2026. In 2027, SpaceX is expected to account for 20%–40% of Nvidia rack shipments, with a base-case assumption of 7GW of new capacity — roughly 21,000 VR200 racks.
All new capacity comes from two greenfield campuses: Starbase in Brownsville, Texas (initial investment over $24 billion, self-built gas power plant, ~3GW expected) and Cochise County, Arizona (initial investment ~$50 billion, full-load power capacity 6GW).
SpaceX's own guidance targets at least 10GW of additions; Musk's goal is over 13GW by year-end 2027. In plain terms = Nomura's base case is already aggressive, but Musk's ambition runs nearly double that — the gap itself is a source of uncertainty.
The Cochise County project's power agreements and land-use permits still await regulatory approval. Nomura flags this as the key milestone for judging whether Musk's targets are achievable.
Can the growth numbers actually be met? Five risks pointing to one question
Nomura's 2027 AI server revenue increment is roughly $522 billion, while consensus capex additions from the top five hyperscalers total only about $331 billion — a gap of roughly $191 billion. This means → either hyperscaler spending estimates get revised sharply higher, or emerging-cloud and SpaceX capital must arrive faster — otherwise the revenue forecast cannot hold.
Nomura's 2028 data-center tracker shows confirmed capacity at just 28.1GW, or 35% of the total; unconfirmed capacity reaches 42.7GW. In plain terms = nearly half the compute supply projected for 2028 doesn't have a confirmed site yet.
Nomura identifies five key risks: regulatory tightening (especially on 2028 data-center permits), financing pressure (emerging-cloud and SpaceX capex scales straining capital markets), continued component shortages, technology switches (e.g., Google TPU v9 moving to EMIB-T), and Nvidia leadership changes creating market uncertainty.
This reflects a fundamental tension: 2028 shipment growth is nearly flat, so revenue growth depends entirely on pricing — but the room for further price increases is precisely what these five risks threaten to close.